Our Work

Download the latest version of our Capability Statement

Worting Junction, South West Mainline, Worting, Surrey

Deconstruction of a decommissioned electrical transformer working directly adjacent to the live mainline railway, our operatives used a crab crane to carefully remove the components which were taken from site during a track posession.

Woodberry Down, Manor House, N4

Demolition of 6 residential blocks to enable Phase 4 of this massive regeneration project in North London was complicated by having a high voltage UKPN transformer in the middle of the site. This six month project will leave the site clear for hundreds of new properties to be constructed on this site.

Swan Wharf, Dace Road, London E3

Over several phases we took this former industrial site back to the structural bare bones to enable the regeneration of the building into high specification residential apartments. Being a waterside site our works had to ensure that no hazard was presented to passing river and canal traffic

Kensington High Street, London

Alpine were asked to step in and remediate works previously completed on this major refurbishment project in the West End of London. Undertaking almost 2 years of demolition, repair and replacement of structural elements allowed this project to be handed over to the fit out contractor to complete the works.

Chailey Industrial Estate,

Hayes, Middlesex

Alpine Demolition were contracted by Fairview New Homes to undertake the demolition and site enabling works on this project as Principal Contractor. This was part of a regeneration project including construction of 331 new homes. Included over 15 thousand square meters of slab requiring crushing

RBS, Lombard Street,

City of London

Alpine Demolition removed 8 above ground and 3 below ground storeys including strip out, asbestos removal and principal demolition works. Retention of structural elements required extensive support installations. Works also included removal of reinforced bank vaults.

Buckland Hospital,

Dover, Kent

This hospital was one of the original NHS Hospitals and parts of it dated back to the 1800s. With a brand new hospital built next door the redevelopment into new housing required demolition of the existing structure. Strict controls in place due to working adjacent to live hospital.

Weetabix Factory,

Corby

Extensive contamination of the soil underlying this historic factory required careful control and decontamination of all arisings. Alpine Demolition worked to ensure the stability of the site as demolition progressed especially when removing the extensive underground structures.

Swan Wharf,

Tower Hamlets, London

As part of a regeneration project Alpine undertook significant temporary works to support the structural alteration of this listed building in an industrial heritage area of East London. Directly adjacent to a live waterway our works included removal of asbestos, diamond sawing and installation of weatherproofing

Courtaulds Factory,

Coventry, W Midlands

Removing heavy plant, remediating large quantities of heavily contaminated soil and the demolition of several chimney stacks whilst ensuring the adjacent canal remained in use. Employing continuous monitoring of noise, dust and vibration we ensured that this vast site was cleared on program.

Global Switch Data Centre,

East India Dock, London

Decommissioning and removal of electrical switchgear and cabling in a live data centre. Using close liaison with the centre managers and strict control of dust and vibration we completed this project with no disturbance to the essential and live comms services around the works

Ford Data Centre,

Brentford, London

Demolition of legacy headquarters building in West London including contamination control measures and a constrained working environment. The superstructure demolition was undertaken using long reach plant, and a large number of underground tanks were also removed.

Got a Project in mind?

Get Your Free Quote